Building a distributed datacenter for the future of AI.
Big datacenters are waiting years for permits and power. We containerize GPU capacity to run on excess power at thousands of small industrial sites around the world.
What it is
Your property. Your power. Our box. Our GPU.
TWR sets a self-contained 20 ft container on a parking pad. Inside are one or two NVIDIA GB300 NVL72 racks, 72 GPUs each. Power and cooling stay in the box. No water needed. The building stays a building. You lease the pad and the power. We operate the racks.
What the property needs is spare 480 volt three-phase power, 250 amps for one rack or 500 amps for two, a concrete pad, and a business fiber line of about 10 gigabits per second. A licensed electrician makes the connection. You do not have to run the computers, and the site does not supply water.
Why
GPU capacity is waiting on sites that take years.
New hyperscale power, substations, and generation take years, so GPU capacity is stuck waiting on big sites.
A 20 ft self-contained container on an industrial parking pad is the way through. Each box holds one or two NVIDIA GB300 NVL72 racks. The property brings the pad, 480 V, and fiber. There is no site water. Many of those small sites run as one distributed compute cloud.
Time to get it
Demand vs the grid, 2025
Published ranges, not a TWR forecast. New transmission is 5–15 years (IEA). US projects that reached operation in 2025 spent a median of over 5 years in the interconnection queue (Berkeley Lab). Substation transformers are quoted past 160 weeks (Wood Mackenzie, 2026). Data-center electricity use rose 17% in 2025, against 3% for global electricity (IEA). About 20% of planned data-center projects are at risk of delay if grid bottlenecks stay (IEA).
Hardware
NVIDIA GB300 NVL72
- 72 Blackwell Ultra GPUs
- 20 TB GPU memory
- 1,440 petaflops FP4
- 130 TB/s NVLink
Per rack, from NVIDIA. The FP4 figure includes sparsity. Dense FP4 is 1,080 petaflops.
Who it’s for
Join the waitlist.
-
Property owner
You have industrial property with spare power and room for a pad. If the power is 480 volt three-phase with at least 250 amps to spare and fiber can reach the site, you lease the pad. TWR brings the box and runs it.
-
Investor
Be the first to know when a site is ready to talk about. Joining the list is interest only, not an offer.
-
GPU reservation
Capacity can be reserved for 1, 2, 3, or 4 years. A longer term has a lower hourly rate and a different share paid up front, and exact terms are shared with people on the waitlist.
Waitlist
Property, investment, or a GPU reservation. We’ll follow up. Nothing here books a pad, takes capital, or reserves a rack.